Microsoft Project :






POSSIBLE PATH:
A +B +C +D+ E+ F+ G+ H  = 90 Days.
A +B +C +D+ E+ G+ H       = 83 Days.
A +B +C+ E+ F+ G+ H        = 80 Days
A +B +C + E+G+ H            = 73 days

v  Latest Finish Time = 95 days

Other criteria:
v  Week starts on Monday
v  Consist of 5 days in a week
v  Holidays = CNY- Feb 3rd&4th, Good Friday- Apr 22nd, Labour Day- May 1st.