Microsoft Project :
POSSIBLE PATH:
A +B +C +D+ E+ F+ G+ H = 90 Days.
A +B +C +D+ E+ G+ H = 83 Days.
A +B +C+ E+ F+ G+ H = 80 Days
A +B +C + E+G+ H = 73 days
v Latest Finish Time = 95 days
Other criteria:
v Week starts on Monday
v Consist of 5 days in a week
v Holidays = CNY- Feb 3rd&4th, Good Friday- Apr 22nd, Labour Day- May 1st.